EPC Project and Surface Facilities

section-ee97cd1
ALCANCE GENERAL

Diseño, Ingeniería y Construcción.

section-22e0144
Filadelfia y Paiva

Desing and construction of the acustic barriers at the Filadelfia and Paiva compression stations

EPC for engineering, procurement and construction as a solution of mitigation of noise and temperature at the Filadelfia and Paiva compression stations. that job include the follow activities:

  1. Previous studies, desing and detail engineering for the Filadelfia and paiva compression stations
  2. Construction license
  3. Civil works for the installation of the barriers
  4. Measurements to verify the compliance of the solution
  5. As built blueprints.

Location: Santa Rosa - Bolívar, San Onofre y Toluviejo, Departamento de Sucre.
Duration: 10 meses (05, 2019 - 03, 2020)

//ccringenieros.com/wp-content/uploads/2021/03/construccion-de-barreras-acusticas-filadelfia-paiva.jpg
section-d2c7343
Paiva

Reengineering and construction of Paiva compression station with capacity 141 MMSCFD

//ccringenieros.com/wp-content/uploads/2021/03/reingenieria-construccion-paiva.jpg

Reengineering and Construction of Paiva Compression Station. That job include the follow activities:

  1. Reengineering for mechanical, piping, civil, electrical and instrumentation works.
  2. Uninstall of the Turbocharger, included the oil cooler at the Ballena station
  3. Uninstall of the microturbine Capstone C600 at Sahagun station
  4. Construction of the Paiva Compression station

Location: Santa Rosa - Bolívar.
Duration: 210 days (02, 2019 - 09, 2019)

section-92114ca
Jobo 130

Construction, support in the comissioning and the start up of a gas treatment plant

which capacity is 130 MMSCFD of gas in rut standar. this job included civil, mechanical, electrical and instrumentation works for optimum performance.

CIVIL WORKS:
Foundations in general, compressor shelter, generation house, and air compressor. Internal ways in granular material, enclousure in mesh, brackets and town planning.

MECHANICAL WORKS:
Procurement and construction of a bridge crane, tanks for process and condensed water. Installation of the main equipments.
(2) Three phases separator which capacity is 65 MMSCFD ea.
(4) Coalescent filterwhich capacity is 65 MMSCFD ea.
(2) Dehydrator TEG which capacity is70 MMSCFD ea.
(5) Reciprocating compressor which capacity is 65 MMSCFD ea. - 1900 HP
(1) Flare system (KOD + Flare) which capacity is 130 MMSCFD
(2) Joule Thompson systemwhich capacity is 65 MMSCFD ea.
Interconexion piping and and metallic brackets.

ELECTRICAL WORKS:
Grounding mesh, conduit pipes, cable tray, cathodic protection, cable installation, conections, lighting, shielding, installation of electrical equipment, installation of MCC, Control Room, CCTV and RETIE certficated.

INSTRUMENTATION WORKS:
PSV calibration, instruments calibration on/off Skid, Fire and Gas System, instruments installation and optic fiber.

Location: Sahagún - Cordoba.
Duration: 8 months (06, 2018 - 02, 2019)

//ccringenieros.com/wp-content/uploads/2021/03/construccion-jobo-130.jpg
section-628927d
Paratebueno

Construction of two compression stations at Cusiana-Apiay y Apiay-Villavicencio-Ocoa gas pipeline.

//ccringenieros.com/wp-content/uploads/2021/03/villavicencio-2-2017.jpg

Construction of two gas crompression station:

Paratebueno from 30 MMSCFD to 64 MMSCFD. installation of the follow equipments:
(3) Compressor which capacity is 32 MMSCFD
(2) Filters
(1) Unit of air compressor
(1) Control room
(1) MCC
(1) Enclosure flare
(1) Slug catcher
(1) Kod
and mechanical, piping, electrical and instrumentation facilities.

Villavicencio from 14,1 MMSCFD to 26 MMSCFD. installation of the follow equipments:
(3) Compressor which capacity is 32 MMSCFD
(2) Filters
(1) Unit of air compressor
(1) Control room
(1) MCC
(1) Enclosure flare
(1) Slug catcher
(1) Kod
and mechanical, piping, electrical and instrumentation facilities.

Location: Paratebueno - Cundinamarca, Villavicencio - Meta.

Duration: 1 year (05, 2017 - 05, 2018)

section-57ffa54
Jobo 100

Construction and assembly of a 100 MMSCFD gas treatment plant within "El Jobo" station, in jurisdiction of Sahagún municipality , department of Cordoba, Colombia

Construction and assembly of a 100 MMSCFD gas treatment plant; with five (5) gas compressors, two(2) three phase inlet separators, two (2) coalescent filters, two (2) teg regen units with btex, one (1) glycol separator, two (2) joule thompson units, one (1) kkod, one (1) flare and its facilities. the project comprised the supply of foundations and structures, mechanical, piping, electrical and instrumentation facilities.

Location: Sahagún - Cordoba.
Duration: Phase 1: 7,6 meses (07, 2015 - 02, 2016).
Phase 2: 5,1 meses (02, 2016 - 07, 2017)

//ccringenieros.com/wp-content/uploads/2021/03/estacion-jobo-100.jpg
section-fbdc6c3
Sabana

Execution of works in civil, mechanical, electrical and instrumentation areas, precommissioning, and support for commissioning and startup of the "La Sabana" gas compression station (ECGSB) from "Transportadora de Gas Internaciona S.A. E.S.E - T.G.I.",

with dynamic technology of continuous flow in the gas pipeline "La Sabana" to compress an average flow of 215 MMSCFD and a maximum of 270 MMSCFD during peak consumption.
//ccringenieros.com/wp-content/uploads/2021/03/construccion-estacion-sabana.jpg

Execution of works in civil, mechanical, electrical and instrumentation areas, precommissioning, and support for commissioning and startup of the "La Sabana" gas compression station (ecgsb) from "Transportadora de Gas Internaciona S.A. E.S.E - T.G.I.", with dynamic technology of continuous flow in the gas pipeline "La Sabana" to compress an average flow of 215 MMSCFD and a maximum of 270 MMSCFD during peak consumption.

Location: Cajicá - Cundinamarca.
Duration: 8 months (09, 2012 - 05, 2013)

section-aadaea6
Termoyopal

Sublicense work for the construction and installation of electrical and instrumentation works and for the interconnection pipes and the truck loading station for Termoyopal gas drying plant, "El Morro" district, Yopal municipality, department of Casanare, Colombia.

Execution of construction and installation works of piping, electrical and instrumentation.

Location: Yopal - Casanare.
Duration: 8 months (09, 2012 - 05, 2013).

//ccringenieros.com/wp-content/uploads/2021/03/construccion-estacion-termoyopal.jpg
section-0c246cb